Categories
Route Alignments

Northern approach – avoiding 4-tracking north of Cambridge

Introduction

The article below has been written by an anonymous Cambridgeshire contributor who has a keen passion for, and knowledge of, railways. The previous article on this subject showed that the general capacity of the existing twin track between Cambridge Station and Milton Junction was sufficient to take the existing traffic, planned growth and EWR trains without the need for 4-tracking.

In discussions and correspondence with EWR Co, it was clear that they have carried out their assessment based on the current timetable. They claim that this showed that 4-tracking of this section of the track would be required. Our previous article suggested that this was unnecessary as the current timetable would change over the next 10 years before EWR became operational.

However, to address EWR Co’s specific concerns, we have looked at the issues that they raise with the timetable and show that, with a minor revision, even on this basis there is no need to 4-track this track.

Summary

EWR Co’s argued need for 4-tracking in the north of Cambridge in a ‘northern approach’ scenario – which underpins their decision to discount that option in the latest consultation – is based on concerns about interfacing with current operations. EWR Co have not published their full analysis, but state that they cannot fit EWR trains at regular 15 minute intervals alongside the existing timetable. While that statement appears to be technically true (in the most tenuous sense), the analysis presents here suggests that without context, it is likely highly misleading – and 4-tracking is certainly not the only solution. The issue is not too many trains, but a few quirky ‘symmetry breaking’ inefficiencies in the current timetable (particularly the fast/slow Liverpool Street trains). The immediate EWR issue can be solved by slipping a single hourly train by a single minute, and even if we are to future-proof to include the reasonable-worst-case scenario (including a variety of other future trains beyond EWR), only very minor tweaks to the existing are needed to make it work. Once Cambridge to Liverpool Street services are expanded to four an hour (expected in a similar timeframe to EWR’s construction), the asymmetry issues will have resolved themselves anyway – so it is illogical to let such quirks control EWR’s design decisions.

1.      Introduction

(I suggest you grab a cuppa and get comfortable before you continue, as this is quite a long and technical post)

I should start by saying that I’m not a campaigner and am not necessarily pushing for any particular outcome. Having seen the significant campaigning efforts of Cambridge Approaches, CBRR and others, however, I thought it would be interesting to delve into the ‘north vs south’ arguments from an objective viewpoint, to try and determine whether or not the proposed northern approach is actually a viable alternative. A few months of late-night analysis later, and yes, I do think there are – potentially – some aspects which may have been overlooked. I am not an industry expert and am of course willing to be stand corrected if I have missed something important, but am keen to open the discussion so that we maximise our chances of building the best railway possible. Although EWR Co have published many pages of technical documents describing the consequences of 4-tracking, they have unfortunately still not provided a robust technical justification for why they think it is necessary – instead simply claiming that they have “looked at it and concluded that it’s the only solution”. This makes it very difficult to peer review their work and assess the validity of their argument, so some guesswork is required in attempting to re-trace their steps. I’ve tried to present everything as clearly and transparently as I can in this document, so people can see the arguments for themselves.

If, as EWR Co claim, the only way to add four hourly EWR trains through Cambridge North is to add a second pair of tracks through the north of Cambridge, then the associated destruction of nearby properties and other infrastructure costs are very significant (as the infamous “appendix F” goes to great lengths to illustrate). These consequences feature front-and-centre in EWR Co’s justification for discounting a northern approach, and I suspect finding a way to avoid 4-tracking is at the core of the northern approach’s viability.

If my analysis has missed some vital other reason why 4-tracking really is the only solution, then the proposed southern approach certainly has its relative merits. However, there is still a possibility that as even more Cambridge-London trains are added, sending EWR trains into Cambridge from the south might mean it isn’t long before the track from Shelford to Harston needs 4-tracking, alongside grade separation of the Shelford junction, both of which would also be highly disruptive.

2.      Mapping the new railway

In the vector diagram below, every line corresponds to a single hourly train in each direction at present (except for the orange freight line, which is just indicative of routes).

Hourly services in each direction: existing (pre-pandemic)

The next diagram is a best guess at how EWR Co’s proposed ‘southern approach’ might look. This analysis is based on an assumed 4 trains an hour, which would be in line with the busiest UK inter-city services running today. I’ve included the potential Wisbech line (either running from Cambridge or splitting from existing trains at Ely), added second hourly trains to both Norwich and Ipswich, and extended a second hourly London train from Ely to King’s Lynn. This gives us a reasonable upper bound for the next few decades to the north and east. I’ve not added potential extra trains south of Cambridge, such as the mooted services to Maidstone or Haverhill, or additional London services (at least three of which are included in Network Rail’s 2030/40 scenarios). There is still some uncertainty about how EWR would be timetabled: I’ve taken the ‘best case’ scenario where Norwich keeps its direct Stansted service, but otherwise 3 of 4 EWR trains continue to Norwich (1/h) and Ipswich (2/h). EWR, then, serves Cambridge South and Central stations with every train; Cambridge North only sees a single hourly EWR service.

Hourly services in each direction: southern approach

Next, we have a potential ‘northern approach’. The same extra services are assumed as above, but EWR now arrives via a junction at Milton rather than Harston. There’s an optional station at Northstowe (and space still for one at Harston too), and 4-tracking may only need to go as far as Cambridge South. In this scenario, the ‘base case’ is that EWR trains all serve all three Cambridge stations, terminating at Cambridge South. There are options, such as linking with existing London (if electrified), Stansted and/or a reopened Haverhill line, or reversing at Cambridge in order to continue towards Norwich/Ipswich. It is a requirement that EWR’s design does not preclude the latter as an option, though it is probably not the most beneficial solution. Freight mostly avoids Cambridge via a new chord south of Ely. This would, admittedly, be expensive to construct (as it would include a new bridge over the Cam), but could remove freight from the single-track Newmarket route, reducing the need to dual quite as much of it.

Hourly services in each direction: northern approach

3.      Improving existing layouts

It is clear from the northern approach diagram that the section through the north of Cambridge is quite busy – so at first glance the argument for 4-tracking seems reasonable. But can it be avoided? The first step is to see what can be done, with only modest adjustments, to increase efficiency in that section. South of Cambridge (central) station we will have 4 tracks, a grade-separated Milton junction confers no additional capacity constraints, so the solution hinges on just the three miles of twin tracks between Cambridge’s central and north stations.

Two hourly Liverpool Street trains terminate at Cambridge North (except for 2/day to each of Ely and King’s Lynn). When they head back south, they block the northbound track until they reach the switch point south of the river. However, this can easily be avoided by moving the terminus platform from the west to the centre. Although it should not be necessary, the through-platforms could be doubled up: There’s space for the western one within the existing footprint, while a 5th on the eastern side will probably take a sliver of land from neighbouring properties. In the very worst-case scenario, if no extra land is available, then there is space further north to stagger northbound and southbound platforms. If, as has been suggested, the two Liverpool Street trains will in future need to continue to Ely, then a terminus here is not required, and either 2 or 4 platforms would suffice.

Cambridge North station – diagrammatic track layout
Cambridge North station – looking north

Cambridge Central is a large and complex station, currently having four terminus and four through-platforms (the latter all serving trains in both directions). The terminus platforms are all on the western side, so reversing trains again obstruct oncoming traffic as they switch tracks. According to Network Rail’s 2019 report, a southern approach would see a new island pair of through-platforms to the east, and 3-tracking to the Coldham’s Lane junction, as shown on the right in the figure below.

Diagrammatic track layout at Cambridge station – existing and Network Rail’s southern approach

There are many possible iterations for upgrading the station in a northern approach scenario. The first obvious step is to swap Ipswich/Newmarket trains onto a new eastern platform. Without the need to weave Newmarket-bound trains across from the eastern side of the Shelford junction as they approach from Oxford, it should be possible to separate them entirely from other services via 3rd track to the east towards the Coldham’s Lane junction. Ipswich trains currently only dwell at Cambridge for about five minutes, so even with two or more such services an hour, a single platform and single track under Coldham’s Lane bridge should be sufficient, assuming most freight is diverted via a new spur near Ely.

It may make sense to tidy the central portion of the station into a pair of northbound and a pair of southbound platforms. In a similar approach to Cambridge North mentioned above, it might also be possible to allocate a terminus-priority platform in the middle (the current platform 7) which could eliminate at-grade crossings on the section we’re interested in. This platform could be extended to the south, to also provide a central terminus for trains from London. If the latter option is chosen, platforms 5 and 6 might even become redundant: paved over, they’d make the ideal location for a second station entrance, providing a much shorter route from cycle parking to the platform bridge, and additional income from renting out retail space.

Cambridge station diagrammatic track layout – two options

It is worth noting that Cambridge central station is more constrained to the south than the north: the Hills Road bridge is just 100 metres beyond the end of platform 1 (and only four tracks wide), and the post office building & car park limits space to the southeast. At present, there is space for the existing platform island to be extended further south – though if the new eastern platform island were connected to the south, this option may become less viable. In a northern approach scenario, there is much better balance in the number of trains heading north vs south in and out of Cambridge, which should reduce the pressure on platform space and time from terminating services.

Cambridge station looking north – existing platforms

For completeness, we should mention Cambridge South. In the southern approach proposal, it has four platforms – two pairs serving ~14/h in each direction (plus any future London services). In a northern approach scenario it may serve slightly fewer trains, but some might terminate at the station. It should be possible for a single platform to cope with as little as 3 minutes between trains (see Tottenham Hale’s southbound platform 1, for example), but in the worst-case scenario a 5th platform may be required here, offering a central terminus and two through-platforms in each direction. Although there would be some opposition to encroachment on Hobson’s Park, the additional land and cost would be very modest (just the width of a single-track path, as the current proposed station design already has the requisite platform island). If few EWR trains terminate here (instead continuing south to a combination of Haverhill, London, Stansted or elsewhere), the chance of needing a 5th platform is reduced, but 4-tracking may instead need to continue to the Shelford junction – as is the case for a southern approach scenario.

Cambridge South station diagrammatic – four options

With a little effort, then, it should be possible (if needed) to entirely eliminate at-grade crossings on the busy section we’re interested in, between Cambridge and Cambridge North. We therefore have a simple scenario of twin tracks, around a dozen trains per hour, and no clashes or constraints linking the two directions. Fewer freight trains should need to use this route (with as many as possible moved to EWR and an Ely chord), so trains should follow very similar acceleration profiles on this short, slow section of track. Nonetheless, we will still aim to ensure one oversized hourly slot remains for freight just in case (because getting as much freight off of the road and onto rail is very much to be encouraged).

If we look at the existing timetables, we see that the minimum gap between trains leaving Cambridge to the north is 3 minutes (xx:00 and xx:03 Cross-Country and Great Northern respectively). A 3-minute headway is also what’s stated in EWR’s requirements [Appendix B 5.7.2 of the latest EWR Co consultation docs] – so we can safely assume this is our minimum acceptable gap. Indeed, it only takes about 3 minutes between leaving one station and arriving at the other, so even spaced this close together, we should never have two trains between the two stations at the same time.  

I should note that the Cross-Country train does not currently stop at Cambridge North station – so despite many examples to the contrary, such as Tottenham Hale mentioned above, EWR Co may still conclude in the worst-case scenario that Cambridge North requires expansion to twin platforms in each direction. This is an expense not required with a southern approach, but that’s only because in a southern approach few (if any) EWR trains actually serve Cambridge North.

4.      Symmetry and inefficiency – the spectre of 4-tracking

In an idealised world without external constraints, 3-minute headings should allow for a theoretical maximum of 20 ‘slots’ per hour (up to 15 of which can be used if we are to stick within the 0.75 resilience requirement). With this in mind, EWR Co’s argument that even the 6 current + 4 EWR trains cannot be accommodated without quadrupling the tracks has led to much head-scratching. So, what is going on; how is the real world so far from ideal that we can’t even manage what is – without even considering future signalling upgrades – just ~50% theoretical capacity?

Although EWR Co have still not published their actual analysis (only the consequences thereof), I recently managed to speak to EWR Co’s Paul Sparrow via their live chat events, and obtained slightly more insight into their analysis:

“We have used some operations specialists to conduct the assessment using rail operations modelling systems in order to ascertain where we could get our 4 trains per hour onto the existing twin track WAML using our regular 15 min clockface service pattern. These results demonstrated that the white space, the space between trains, does not exist to allow us to get 4 trains an hour every 15 mins.” (Paul Sparrow, 29th May 2021)

This snippet of information, although still quite cryptic, is perhaps just enough for us to solve the mystery. The issue, I now suspect, is actually quite simple – and it’s all down to symmetry. Despite computational advances, building railway timetables is still ultimately mathematically driven by repeating patterns: it’s what the Swiss call ‘taktfahrplan’, or clock-face scheduling. Most train lines interact with several others along the length of their routes, and weaving all of these interconnected requirements together without clashes is much easier if everyone is dancing to the same beat. Although modern timetables may look quite random, they are essentially still just perturbations on an underlying regular symmetry.

We can illustrate this with a simplified example. Consider a railway line serving four locations: Appletown and Bananaville each need four trains an hour; Carrotbridge and Donutland need two apiece. Treating C&D as a single set, we can schedule these 12 trains at 5-minute intervals, with a pattern repeating every 15 minutes (left clock-face below). However, what if Carrotbridge decide they need their pair of hourly trains spaced 20 minutes apart? We start with Appletown’s regular trains, but once we’ve added Carrotbridge’s symmetry-breaking requirements, there’s no space left for Bananaville to have a train every 15 minutes. We can squeeze in the pair of Donutland trains, but the remaining slots are unhelpfully distributed – poor Bananaville!

This scenario is conceptually very closely related to the issue we have at hand. Carrotbridge in this case is represented by the Greater Anglia trains to Liverpool Street – and Bananaville is Oxford!

The two hourly trains from Cambridge North to Liverpool Street arrive in London at regular half-hour intervals. However, one of them is slightly ‘fast’ and the other ‘slow’: the difference is a modest ~10 minutes (~1h10 vs ~1h20). In order to make this work, 30 minutes after the slow train has left Cambridge North, the fast train…sits there for another 10 minutes, and then departs. By stopping at fewer stations on route, by the time it reaches London it has caught back up again to the 30-minute periodicity. On the return leg back north, the fast train arrives back 10 minutes earlier than its slow train equivalent would have done, and so it ends up sitting at Cambridge North…for yet another 10 minutes.

The other trains all tend to run at roughly regular half-hourly slots, into which it would normally be quite easy to add an EWR train every 15 minutes, because their symmetries are in sync. The Liverpool Street train’s timings, however, makes this simple task so much more difficult. As we will see, there are a few other minor quirks in the existing timetables too, all of which can be dealt with quite easily.

5.      Building more efficient timetables

Let us consider how this would work in terms of timetables. We’ve removed all at-grade crossings from the section, and Newmarket-bound trains have been moved onto a separate track. This should make our task relatively straightforward, as we have a single stretch of dual track between Cambridge Central and Cambridge North, with one train simply following the one in front. This is the most constrained section, so if it can be shown to work then everything else should fall into place.

We can start with the current timetable, and then see how the new services might look added in the ‘white space’. In this example, a normal weekday between 1pm and 2pm has been used – the differences from hour to hour are quite minor, so a proof-of-principle assessment needn’t replicate the analysis for every hour of every day. Instead of showing you lots of graphs and lists of timetables, I’ll stick with the ‘clock-face’ diagrams from the Appletown example above.

In the clock-face diagrams below, each service is represented by a 3-minute block, during which no other trains may depart. In the current timetable, we can see the two closest trains’ blocks adjacent to one another at xx:00 and xx03 on the northbound chart, and vast swathes of free ‘white space’ in both directions. These really aren’t very busy lines at the moment, with a train on each track between the stations just 30% of the time! But as you can see, the pairs of trains to Liverpool Street and (in the southbound direction) King’s Cross are not nicely symmetrical, with the Norwich train sitting where one might expect the second Liverpool Street train to be.

Now, if we attempt to add four hourly EWR trains to the existing timetable, it might look something like the figure below. At first glance all seems fine, but on closer inspection one of the four EWR trains has been slipped by a single minute from its ideal 15-minute-interval service, in order to avoid overlapping with an existing train’s 3-minute window. Although you might think this a very minor issue – arising from an existing timetable quirk which will long since have changed by the time EWR is built – as far as I can tell (going by Paul Sparrow’s above quote), it is precisely this which has led EWR Co to claim that the only solution is to build two more tracks through the north of Cambridge!

Nonetheless, sticking for now with the nearly symmetrical EWR trains added alongside the existing timetable, what other services might we need to make room for in the next few decades, to ensure our design is future-proof? A second Norwich train is an obvious one: Northbound it can fit exactly 30 minutes away from the existing train; southbound we have to offset it by a couple of minutes from its ideal position (one bit of broken symmetry forcing another one). After this, there is still space for another half-hourly service (e.g. trains to Wisbech) – and we’re still within the 75% resilience threshold stated in EWR’s requirements [Appendix B 5.7.2]. In both directions, there’s an oversized gap left in the hourly timetable for even a very slow freight train to get through, although this should be avoidable in most instances as freight could travel via Soham or Newmarket instead. We could even (not shown) double up the Birmingham service (which some hope could be extended to Leeds in future), by simply moving the northbound freight slot to ~xx.45.

The figure above illustrates how a northern approach – and a bunch of potential other future services – could work, without any changes to the existing timetable, without any signalling upgrades, and within the documented requirements of headways (3 minutes) and resilience (25% unused wiggle-room), without resorting to knocking down any buildings to build more tracks. However, what if we absolutely must have a symmetrically perfect-to-the-minute EWR service? Or, indeed, what if we would just like to tidy up the existing inefficient broken symmetries, and thus optimise the potential capacity through Cambridge’s only traffic-jam-avoiding cross-city travel corridor?

Northbound, the solution is incredibly simple. The fast train from Liverpool Street (which is about to sit at Cambridge North for more than half an hour) can just wait for a single minute at Cambridge station. That’s it.

Southbound, we have slightly more work to do. First, we align the time for which the King’s Cross trains dwell at Cambridge. I suspect the reason for this asymmetry in the current timetable comes from train-splitting, but with platforms at Ely and Waterbeach due to be extended, Network Rail themselves expect that procedure to be phased out in the coming years. Next, we have the fast Liverpool Street train (which leaves 10 minutes later than symmetry would like), and the existing Norwich train (which is then in the way). A neat, symmetry-restoring solution (as shown in the diagram below) is to push the Norwich train back by two minutes, and have the fast Liverpool Street train depart Cambridge North 10 minutes early, and dwell at Cambridge for 10 minutes (where it will be overtaken by the Norwich train, and then continue to Cambridge South roughly alongside the EWR service on the quad tracks). This would only be needed until two more (slow) trains between Cambridge Central and Liverpool Street are added, at which point both Cambridge North to Liverpool Street trains can become fast services.

The Norwich train, in ensuring regular hourly cycles, has a few minutes of wiggle-room to play with, but in a worst-case scenario it might miss its Stansted spot – in which case its lost slot could be taken up by an EWR train instead. A slightly less neat, but probably still workable and arguably less disruptive, solution (not shown) would have the existing Norwich train unaffected, the fast Liverpool Street train leaving just a minute or two earlier than it currently does, and the second Norwich train 32 minutes after (or 28 before) the existing one. These solutions involve very minor tweaks to the existing timetables, none of which should have any further knock-on effects on other services.

The above is, I would argue, a reasonable worst-case scenario for the 2040s, and is still acceptable within EWR Co’s given requirements. However, I suspect reality will be less constrained, as there are a variety of possible options which would each reduce the number of trains travelling through the busy corridor.

I would be slightly surprised if EWR needed four hourly trains, at least for the first decade or two. Even the busiest UK intercity services such as London to Bristol only have that many – as does Cambridge to King’s Cross (if we ignore the two slow trains which offer no utility for intercity passengers). EWR only serves relatively small towns and cities, and long-distance trips across the country which really aren’t that popular (and are mostly already quite doable via London, especially once Crossrail is operational). Half-hourly 8-carriage trains would have the same capacity as the proposed four hourly 4-carriage ones, and as EWR doesn’t really serve busy commuter routes east of Bletchley (where it’s expected that another 2/h will run from Oxford to the Milton Keynes  branch anyway), I suspect few would be very upset by a slightly less frequent service. Other than for a few select local routes (such as Cambridge and Bedford residents hopping on the train to Bletchley’s IKEA), EWR provides (at best) a modest improvement rather than a genuine transport revolution. Let’s just hope the trains have enough luggage space for flat-pack bookcases!

Next, it’s worth noting that Wisbech and King’s Lynn are a similar distance from Ely. The fast King’s Cross train, which currently splits at Cambridge (with only the front section continuing further north) could instead continue as one further north beyond the new Milton junction (where the track is less congested). It could then split in half at Ely (or the new Waterbeach station), with the front continuing to King’s Lynn, and the back departing for Wisbech three minutes later.

We could go further still. There are actually two routes from Norwich to Cambridge, of similar length. The route currently operating heads via Ely, but there’s another route via Diss and Bury St Edmunds. A direct train using the latter would either need to reverse in Stowmarket, or use a yet-to-be-built spur just north thereof. If a second Norwich train took this route, it would provide direct connections between Cambridge and Diss; Norwich and Bury St Edmunds. Moreover, while a large fraction of trips to Cambridge on the Norwich train involve people travelling the whole length of the line (with small numbers using intermediate stations such as Thetford), most Cambridge arrivals on the train from Ipswich come from Newmarket or Bury St Edmunds. Therefore, instead of having two Norwich trains via Thetford and two Ipswich ones via Bury, sending the second Norwich train via Bury may actually better serve passenger demand – as well as easing Ely’s congestion problems.

As a final potential tweak, it’s worth thinking about how to make best use of the station at Stansted Airport. Airports are the one location where direct trains are hugely advantageous, as swapping trains at intermediate stations is much more difficult if you have heavy luggage in tow (or are jetlagged!). However, the long single-track tunnel under the runway severely restricts how many trains can reach the airport. From Cambridge, two hourly trains make the journey – one from Norwich (Greater Anglia, class 755 diesel/electric hybrid trains) and one from Birmingham (Cross-Country, class 170 diesels). Could we use the advent of “Great British Railways” to shuffle rolling stock around, and thus find a way for these two trains to join together (at Ely or Waterbeach) and travel as one to Stansted? GA has a whole bunch of class 755s on local routes, a few of which could perhaps be swapped for CC’s class 170s – and I see no reason why the resulting 755 pair couldn’t couple together. This would then free up a Stansted slot, which (in a northern approach scenario) could enable an hourly direct EWR train from Oxford to Stansted!

If we put all of the above together in an optimistic scenario for the 2040s, we actually find ourselves with just a single extra train each hour compared with the current timetable (and even that is offset by an expected reduction in freight traffic, given a new spur south of Ely). I appreciate that at least some of the suggested optimisations might prove unworkable, but nonetheless it reinforces how many different options there are for ensuring there is absolutely no need to four-track through the north of Cambridge in a northern approach!

6.      Has this solved the problem?

The above examples show that there doesn’t appear to be any fundamental issue with scheduling all the trains we might possibly need in a way which avoids the need for 4-tracking. None of the tweaks suggested should cause any knock-on effects, so could be achieved while keeping all other timetables intact. Passengers boarding at Cambridge North towards Liverpool Street may see their southbound journey time increased by a few minutes – but I suspect that is an acceptable price to pay, given that a northern approach (unlike a southern one) would bring a regular EWR service to Cambridge North.

However, it is worth stressing that by 2030 (when EWR is expected to begin operation), the current franchises will be long gone: The current Greater Anglia franchise ends in 2025, and Great British Railways is about to completely shake up the way franchises work in the UK anyway. As such, so long as the *principle* of operation is sound, it’s not really worth worrying in fine detail what the precise timetables will look like at this stage – because they’ll all have changed by the time the line is built in any case.

It is, of course, worth noting that even in a southern approach scenario, the frequency of trains will increase – and symmetry-breaking carbuncles, which massively reduce line capacity, will need to be phased out regardless. The Liverpool Street asymmetry will probably be eliminated entirely within a few years anyway, as we expect to require a new pair of WAML trains which terminate at Cambridge Central. With four hourly trains in total, the Cambridge North pair will almost certainly both be designated as similarly ‘fast’, At which point the whole asymmetry issue disappears!

When designing new, it is always better to start as cleanly as possible, rather than adding yet more mess on top of existing inefficiencies. As the existing quirks can be easily tidied up – and will probably need to be resolved soon anyway – it would be wholly irrational to base major infrastructure design decisions around them. Nonetheless, given EWR Co’s claimed arguments, I thought it useful to illustrate how I think 4-tracking can be avoided both in principle, and in practice around the current timetable.

I haven’t considered in detail the extra services to London which Network Rail’s forecasts indicate will be needed by 2040. Most of these won’t pass north of Cambridge Central, so will not affect a northern approach. Looking at NR’s worst-case 2043 scenario, the only extra services needed north of Cambridge are one or two more Ely-KX trains (which could be the Wisbech trains, already factored into my model) and extending the two existing Liverpool Street trains beyond Cambridge North to terminate at Ely (which would remove the need for a 5th platform at Cambridge North, but add no further constraint issues so long as the junction at Milton is grade-separated). On the other hand, they will add further pressure to a southern approach, which even with 4-tracking may find the south Cambridge corridor eventually becomes problematically congested – risking platform capacity issues at Cambridge Central from so many terminating trains, and perhaps a need to rebuild Shelford junction as grade-separated.

7.      Concluding remarks

EWR’s Paul Sparrow has stated that the existing timetable doesn’t “allow us to get 4 [EWR] trains an hour every 15 mins” for a northern approach. The analysis presented here appears to confirm that this is technically a correct statement, but – unless I am very much mistaken – only in the same kind of way that I can say I was Time Magazine’s Person of the Year in 2006: It’s only *just* correct, and likely very misleading for them to have used it to draw the conclusions they have.

EWR Co claim that the only solution to the above, in a ‘northern approach’ scenario, is to 4-track north of Cambridge station. I disagree. The immediate EWR issue can be solved by slipping a single hourly train by a single minute, and even if we are to future-proof to include the reasonable-worst-case scenario (including a variety of other future trains beyond EWR), only very minor tweaks to the existing timetable – which will almost certainly disappear soon anyway – are needed to make it work.

If my analysis turns out to be sound, then I do not understand why EWR Co decided that 4-tracking (with dozens of demolitions, new bridges etc) is considered a lesser evil. I accept that there may be additional complications of which we are not aware, and which render the proposals in this document unworkable – but if that is the case, then they absolutely must be able to explain to the public why this is the case, and cannot continue to simply state “our modelling says it is not possible” without offering a technical justification.

If the timetabling issue can be resolved and 4-tracking rendered unnecessary, the question of a northern vs southern approach becomes much more balanced. I will leave it to others to expound the pros and cons of each option, but advantages such as keeping more freight out of Cambridge, EWR regularly serving Cambridge North (and potentially also London and/or Stansted), the option of a station at Northstowe (offering direct links to Cambourne, Oxford and Addenbrookes), an easier way to get the Haverhill line back up and running (without it adding even more N-v-S imbalance to the numbers of trains running through the Cambridge corridor), and simplifying the process of electrification between Oxford and Cambridge by decoupling from the Eastern section (not due for upgrade until 2040-50)…are all worth thinking about very seriously indeed.

Categories
Route Alignments

Do EWR Cambridge Approaches Need 4-Tracking?

Why do we need to know about 4-tracking?

EWR Co’s decision to prioritise a southern approach into Cambridge primarily hinges on their assertion that a northern approach will require to be 4-tracked from the Milton junction with the existing West Anglia Main Line (WAML) into Cambridge. They also say that the existing Shepreth Branch Line between Hauxton Junction and Shepreth Junction (SBR) does not need to be 4-tracked but accept that this assessment needs further testing in later design stages.

Fig 1 – Northern and southern approaches into Cambridge with EWR Co’s 4-tracking proposals

It is vital that these matters are properly assessed now. To implement 4-tracking on either of these sections of existing lines would be extremely expensive. Major existing bridges would need to be modified or rebuilt and other infrastructure modified. If it is not resolved now, detailed design work would proceed based on a potentially faulty premise with the risk of locking the project into a solution that will lose valuable benefits of the alternative route.

To test EWR Co’s assessment, we have carried out our own evaluation of both their claims. We start by looking at the likely number of trains on the sections of the lines in question. We estimate the total number of trains likely to use the line including current traffic and probable growth for both passengers and freight. We discuss the likelihood of each of the scenarios occurring in practice and compare these rail traffic estimates with the capacity of the lines.

Summary

We found that EWR Co’s conclusion about the 4-tracking of the northern approach section NA2 is incorrect and that, for our estimate of the reasonable worst-case scenario, it does not need additional tracks. In fact, even with just traditional signalling there is likely to be sufficient capacity. With digital signalling, which is already specified by EWR Co, we expect there to be over-capacity.

Likewise, the southern approach section of the SBR line can probably take the reasonable worst-case passenger rail traffic estimate (which are based on Network Rail’s figures up to 2044). However, interfacing with the Thameslink services will impose severe restrictions on possible growth in traffic in excess of the figures shown due to anticipated expansion after 2044 as a result of the Ox-Cam Arc plans. The SBR line would not be able to accommodate EWR’s 6 trains per hour that are specified in the Project Wide Output Specification. The freight services estimated by Network Rail may not be able to be fully catered for because of limitations on the Newmarket line.

If EWR Co are wrong in their assertion that the SBR line does not need to be 4-tracked, the construction work that would be required exceeds the theoretical (but unrealistic) case for 4-tracking part of the northern approach.

Rail Traffic

The reasonable worst-case rail traffic scenarios for the northern and southern approaches to Cambridge are shown in Table 1. For the northern approach, we have considered the likely rail traffic on the critical section between Milton junction and Coldham’s Lane. All Newmarket trains would use platform 8 at Cambridge station enabling those services to avoid crossing movements between Cambridge Station and Coldham’s Lane. There is sufficient space in that length to increase the number of tracks should this be required.  

Table 1 – Reasonable worst-case rail traffic scenarios (trains per hour (tph) in each direction) for each approach into Cambridge

The assumptions and data sources used in compiling Table 1 are discussed below.  

  • We have not assumed any long-term change in the pre-pandemic forecasts for growth and and ‘existing’ services due to impact of COVID, even though this is likely to reduce the amount of rail traffic in the short and perhaps the medium term.
  • For consistency and independence, we have used Network Rail’s 2019 Cambridgeshire Corridor Study [Ref. 1] for assessing passenger and freight growth forecasts on the existing network for the two approaches. This will allow a fair operational comparison to be made between the approaches. We have resisted the temptation to consider in this assessment the beneficial effects (for a northern route) of an alternative future route via Newmarket for Norwich trains which has been suggested for many years, or the possibility of March trains splitting/joining other services at Ely. Combined, these could potentially reduce demand on the northern approach by 3tph. Nor have we considered the impact of a potential new Thameslink service between Cambridge and Maidstone East which may increase demand on the southern approach. Lastly, we consider that, if the Ox-Cam Arc proceeds as planned, there would be demand for even more Kings Cross services than mentioned in the Cambridgeshire Corridor Study with a timescale to 2044 only.
  • Future demand for freight on EWR is taken from a scenario suggested by Network Rail in the EWR Co’s Technical Report 3.10.7.
  • For a northern approach, EWR freight would be diverted northwards onto the WAML from Milton via a new grade-separated junction and then onto the main Felixstowe to Nuneaton freight line via a new chord just south of Ely. Any residual freight needing to pass through Cambridge would be planned out of peak hours.

Capacity

Basic ‘open-track’ Assessment

In addition to the basic number of trains per hour that could use an open railway line, the capacity is affected by a number of other factors, including timetabling, any crossing movements between tracks, whether the section of track is between junctions or between stations and the mixture of freight and passenger services. We start by looking at the open-line capacity and then go on to consider these other issues.

(i) Traditional signalling

Traditional signalling systems would allow for about 15 trains per hour with no other compounding factors. This is based on international standards (International Union of Railways or UIC which is the international rail transport industry organisation); a headway (the time between trains) of 3 minutes, as convention and a minimum required by EWR Co (Technical Report Appendix B 5.7.2); and a resilience ‘safety factor’ of 0.75 (UIC Code 406 for mixed traffic lines). The reasonable worst-case scenarios for both the northern and southern approaches as shown in Table 1 appears to be within the capacity of the existing twin track based on open track conditions and traditional signalling.

(ii) Digital Signalling

However, digital signalling will be used by EWR [Ref. 2] One of the benefits of digital signalling is the additional capacity that it provides. UIC have shown that on main railway lines, the capacity increase of ETCS level 2 (with ‘block’ lengths of 400m) over ETCS level 1 could be about 37% [Ref. 3]. This is supported by a statement by Network Rail quoting capacity increases ‘of up to 40%’ [Ref. 4]. These figures should be used with care, but they demonstrate that there would be a real and significant increase in capacity. Even using a capacity increase of half of these amounts, the number of trains per hour able to be accommodated could be increased to 18 by digital signalling without the need for 4-tracking,again without any complicating location-specific issues.

Importantly, digital signalling will also allow bi-directional running on tracks. This can provide significant flexibility, especially at stations, for reversing trains.

Other Factors in Capacity Assessment

There are several factors that could reduce actual capacity on a line, including whether clock-face timetabling is used (which is it on EWR) and the number of crossing of main lines radiating from London. Below we only consider those issues that are different between approaches.

(a) The Thameslink Effect and Slow Trains

Capacity reduction can arise when other train services use the section of track and the times of those services are not possible to change. This occurs for the southern approach where Thameslink services use the track. This leads to tight and sensitive interfaces with those services. The result is that the existing 6 passenger services are almost immutable because they form part of the complex Thameslink network and the East Coast Main Line traffic. The complexity of Thameslink can clearly be seen in the map[5] below, especially all the strands of services coming together in central London where it is planned to have 24tph crossing the Thames (which, incidentally, would not be possible without the capacity-enhancing benefits of digital signalling). EWR Co are very likely to be faced with predetermined ‘paths’ (planned slots for trains) at the Cambridge end of the route that do not mesh with their required paths elsewhere. This poses a serious risk to the effective capacity of this line, the outcome of which can only be resolved when timetabling of services is attempted. This is not the case for the northern approach.

If that were not sufficiently restrictive to the timetable, this line also has a slow service calling at all stations without a ‘loop’ or overtaking section for faster trains before they reach the East Coast Main Line near Hitchin. This means that timetabling for fast trains needs to allow for these slow trains, which will lead to greater gaps between trains. There are minimal such restrictions for a northern approach.

Fig 2 – Thameslink services – note number of lines passing through central London

(b) Crossing Movements and Junctions

Crossing movements required across other tracks and junctions can also reduce the capacity of a line. In the case where junctions are flat (‘at-grade’), one train joining another line could have to wait if another train were using the section of track the first one wanted to use. ‘Grade-separated junctions’ involving ramps and bridges over lines significantly reduce this delay. The southern approach into Cambridge has two junctions (Hauxton and Shepreth Branch junctions) compared to just one for the northern approach.

The northern approach allows trains that are temporarily blocked by other trains to wait for a short time at Cambridge North station. This would allow following trains to also wait at Cambridge North (obviously on another platform) and so minimise any concertina-type delay. On the southern approach, conversely, delayed trains would have to wait in line between junctions, magnifying the impact of such a delay.

(c) Freight

Operationally, slower freight and more speedy passenger services do not mix well. Freight on a northern approach (via a new northbound chord at Milton onto the WAML and then onto the Felixstowe to Nuneaton line via another new chord south of Ely), means that freight would have no impact on EWR operations in the busy section between Milton junction and Coldham’s Lane junction. Conversely, freight and passenger traffic on a southern approach intermingle, potentially resulting in less overall capacity. If the line were eventually used for even slower moving, heavy-haul freight, such as building materials, this would only exacerbate the situation.

For a southern approach, the Cambridgeshire Corridor Study estimates that the Newmarket line, even with the anticipated dualling between Coldhams Lane junction and Teversham, could accommodate 1tph for freight during off-peak hours. Network Rail estimate the freight demand could be 1.3tph during an 18-hour window (i.e. including peak and peak hours), assuming the scenario suggested by Network Rail in the Technical Report 3.10.7. This implies that there could be insufficient capacity on a southern approach for the anticipated freight.

Another operational disadvantage of a southern approach is that because freight needs to pass through Cambridge and Cambridge South stations, the problem of platform provision in both locations would be exacerbated.

What Do EWR Co. Say?

Northern Approach

EWR Co have stated (Appendix F, 2.2.4) that the results of their analysis of a northern approach showed that there would be several conflicting movements between EWR and other services including:

  • Trains towards Ely and eastbound EWR services conflicting where EWR services join the WAML; and
  • Conflicts on various platforms at Cambridge station.

We find the first point hard to understand as there could be a grade-separated junction at Milton specifically to overcome this issue. We find their conclusion that the only remaining option is ‘to add two extra tracks to the WAML, making it a four-track railway between the new Milton junction and Cambridge station’ (Appendix F 2.2.10) curious when they could much less onerously provide a grade-separated junction at Milton than the 4-tracking option. Confusingly, they then state in Appendix F 2.2.12 that ‘a grade-separated junction is required where the EWR route joins the WAML…’.

The second point would be overcome by the construction of two more platforms at Cambridge station which EWR Co already confirm would have to be done (App F section 2.2.10). Interestingly, they fail to mention that the southern approach also needs two new platforms at Cambridge station (Technical Report 11.1.5 ). Indeed, as we will see later, there is more pressure on Cambridge station platforms from a southern approach because a freight service will need to pass through. CamBedRailRoad documents[1] provide a solution without the need for additional platforms at Cambridge.

Southern Approach

EWR Co state (Technical Report 11.4.1): ‘…it is most likely  that the SBR can remain as a twin track railway as there is sufficient existing capacity to be able to add the EWR services required to achieve the Project Objectives and leave spare capacity for an increase in services in the future.’ (Our underlining). So they have not confirmed this vital point before choosing a southerly route.

They go on to state: ‘The working assumption for the operational timetable will be assessed further in the next design phase to confirm that it is correct. The focus will be on timetable and performance modelling of the SBR to ensure that both the EWR and GTR services can run as required with suitable resilience to allow for delay, disruption, and updates to service patterns.’

They appear to acknowledge from the last statement that there could be a problem of interfacing with existing services but without being explicit about it. The Sponsor’s Requirements (App A, 5.3 and 5.4) oblige them, as far as practical, ‘to be resilient to any periods of poor performance on the wider network’ and to ‘isolate the wider network from any periods of poor performance on the Railway [EWR]’.

We consider that such a fundamental point as this should be resolved at this stage or, if it really cannot be resolved now, to base decisions on a risk-based approach (i.e. they should analyse the chances of success and the costs of each scenario) in making the choice between a northern or southern approach.

EWR Co mention that two more platforms are required at Cambridge station for a southern approach. This it is not necessarily just a case of removing some sidings to add an extra pair of platforms at the east of Cambridge station: the Royal Mail building really isn’t that far away, and may need to be removed or reduced to allow space for the extra switching tracks, particularly if another pair of side-by-side platforms are needed. Additionally, there is a very short distance between the platforms at Cambridge station and Hill’s Road bridge, in which space all the different platform tracks need to condense down to just four tracks. Indeed, that itself could become quite a bottleneck for a southern approach, as each of the various trains from London and Oxford terminating at Cambridge need to reverse & switch on their way back out.

Other Issues With Approaches

Although the above sections attempt to show whether the two approaches need to be 4-tracked, there are other arguments that need to be considered in the choice of route from a railway operations and cost viewpoint.

1. Symmetry

EWR Co state (Consultation Document page 52) that trains using a northern approach would need to terminate at Cambridge South station. Similarly, a southern approach would need to terminate at Cambridge North station since this area is also an important employment hub.

If EWR Co persist in their conviction that a northern approach would need to be 4-tracked south of Milton, a southern approach would also need to be 4-tracked to Cambridge North as it would carry at least the same amount of rail traffic. This means that, according to EWR Co’s logic, 4-tracking on this section would be needed whichever approach were adopted.

We fully understand some of the severe practical difficulties in providing this. But this underscores our assertion that the northern approach, by providing relatively easy access to all three stations in Cambridge, serves Cambridge’s employment needs better than does a southern approach.

2. Risk and Impact on Infrastructure

We have already referred to the risk of EWR Co being wrong in their future assessment of whether the Shepreth Branch line would need 4-tracking between Hauxton and Shepreth Branch junctions. If they were wrong, the structures that would require to be constructed or modified specifically for 4-tracking are:

  • M11 crossing
  • River Cam crossing
  • Widened cutting E between Cam and A1301

The first two items are major construction works in their own right.

This list is in addition to those that are required even if 4-tracking is not required, including:

  • Hauxton grade-separated junction,
  • Harston level crossing changes,
  • A1368 bridge rebuild,
  • Hauxton Road level crossing changes,
  • A1301 (rebuilt bridge likely if grade-separated junction at Shepreth Branch junction)
  • Shepreth Branch grade-separated junction.

Clearly none of these 9 structures would require to be constructed if a northern approach were adopted.

Compare this to the two structures (the level crossing near Milton and the A14 crossing) that EWR Co state would be required if 4-tracking were required for a northern approach (which we, as detailed above, strongly refute). The other structures requiring modification (Fen Road, river Cam crossing, Newmarket Road and Mill Road) would need to be carried out anyway as a southern approach needs to terminate in Cambridge North station (see point 1 above). But all these works are less than those required for a southern approach.

This discrepancy in construction works between the approaches demonstrates EWR Co’s apparently sanguine approach to risk-based decision making.

3. Reversing Move at Cambridge

EWR Co have made much of the fact that a reversing move (i.e. the driver changing ends of the train) would be needed in Cambridge for onward eastbound traffic.

Two points are worth highlighting here. Firstly, it is not much of a penalty at all. A train approaching Cambridge from a southern approach would need to stop in the station for approximately 3 minutes before proceeding. For a train from a northern approach, the maximum time for the driver to change ends is about 5 minutes – a difference of some 2 minutes!

The second point is that onward eastbound passenger services are excluded from EWR Co’s remit. Although they need take such provision into account (the Sponsor’s Requirements 1.6 state that ‘Consideration should be given to the provision of or integration with services beyond the Oxford Cambridge sections…’), using this weak argument against a northern approach highlights their lack of strong arguments. It is especially rich when, in response to our queries about the problems that a southern approach would cause with freight east of Cambridge, EWR Co claim that it is not within their scope.

Conclusions

  1. The northern approach would not need to be 4-tracked between Milton junction and Cambridge station for the predicted maximum amount of rail traffic including future expansion of services to Wisbech and Norwich. As a result of digital signalling, it could also cater for EWR Co’s aspiration of 6tph. EWR Co have appeared to ignore a grade-separated junction at Milton in their analysis of 4-tracking of this section.
  2. It is not certain whether the southern approach between Hauxton and Shepreth Branch junctions (SBR line) can take any growth in passenger rail traffic beyond EWR’s 4tph until further timetabling work has been carried out by EWR Co. This is because of the severe constraints imposed by Thameslink and other services using the line. It would certainly not be able to provide capacity for the 6tph EWR services stated in the PWOS. This lack of flexibility to provide for growth is contrary to the Sponsor’s Requirements.
  3. If EWR Co’s future assessment of the SBR line shows that they do require to 4-track it, the construction works required is likely to exceed the theoretical additional works required for 4-tracking the northern approach (as stated in conclusion 1, they are not actually required).
  4. EWR Co have not been transparent about the adverse impact of freight using a southern approach on railway operations.

References

[1] Network Rail Cambridgeshire Corridor Study 2019.
[2] Programme-Wide Output Specification (Technical Report Appendix B 5.20.2) is ‘at least’ European Train Control System (ETCS) Level 2. The current signalling system in the general Cambridge area on existing track (i.e. in addition to the EWR track) is being upgraded to provide a platform ready for digital technologies and is planned to be complete by 2025, five years before the currently planned EWR completion date.
[3] ‘Influence of ETCS on line capacity – generic study’, UIC, Fig 24
[4] https://www.networkrail.co.uk/running-the-railway/railway-upgrade-plan/digital-railway/
[5] By Mvpo666 – Own work, CC BY-SA 4.0,
[6] CBRR Northern Approach Into Cambridge.

Categories
Route Alignments

EWR’s ‘Comparison of Factual Data’ Tables

Background

EWR Co’s Appendix F to the Technical Report contains two tables comparing the northern approach into Cambridge with the southern approach using a variety of parameters. They include such factors as length of viaducts, impact on residential areas, number of bridges required and impacts on environmental sites such as SSSIs and scheduled monuments. Cambridge Approaches has carried out a similar exercise months before East West Rail and presented the conclusions to the press, to EWR and to the rail minister. The tables from EWR Co are in response to our work. Now that we have confirmation of the route and the results of EWR Co analysis we have updated our assessment as shown in this post to show what we believe is a fairer comparison between the routes.

EWR Co presented their comparison tables to local councillors on the opening day of the of the consultation with a table entitled “actual facts”. We are not sure if this is a reference to a belief that CA analysis is wrong or whether they mean that the rest of their consultation does not contain “actual facts”. Perhaps they can clarify.

Our results very clearly contradict EWR Co claims of an advantage for the southern route. In most cases the total reverse is true. For the few remaining counts, the result is broadly balanced. The main reasons for the difference in conclusions are what factors EWR Co have decided to measure, the assumptions they have made and how they have chosen to measure their figures.

Assumptions and Measurement Points

One important assumption that EWR Co have used to underpin their case is that the West Anglia Main Line (WAML) would require to be 4-tracked (increasing the 2 existing tracks to 4) from where a northern approach would join the WAML at Milton and Cambridge. We believe that this would not need be carried out and we will explain our thinking on this in another post. As a result, we have, for some items, provided two counts – one with the 4-tracking (for direct comparison with EWR Co’s own figures) and one without 4-tracking (which we believe is more realistic).

We have also, in some cases, used two measuring points to gain a more accurate assessment of the factors. EWR Co have consistently used only Cambridge station as the basis for comparison between approaches. This may be reasonable for passenger trains but for freight trains, Coldham’s Common is more appropriate since that is the point where freight trains from the two approaches diverge. A freight train is generally accepted to be noisier than an electrified passenger train and just because EWR Co. will not be operating the freight train themselves, it does not mean that the noise will not wake residents in the middle of the night. A map of the area is shown in Figure 1.

EWR Co have said that they have combined the two northern approach options (i.e. freight passing via a new chord just south of Ely and freight passing via a new chord on Coldham’s Common). They have, notably, omitted to mention any of the advantages of the former option in their comparison of factual data. In particular, there would be no impact of freight on Cambridge residents if our first option were adopted and much less overall. For clarity in comparison of numbers, we have used the Coldham’s Common chord option for measurements.


Figure 1 – Route options and measuring points

Results

Analysis

General factors

Operational length

EWR Co recognise that there is little difference (1.1km) between the track lengths of the two approaches for passenger trains measured to Cambridge station. However, the northern approach is over 3km shorter for freight using the Coldham’s Common chord.

Length of infrastructure

While the northern route passes through a greater length of flood zone, it plays this to its advantage by adoption of a trench solution which utilises the buoyancy effect in the waterlogged ground. This results in no viaducts and minimal embankments. It passes beneath roads and the guided busway and could be constructed while keeping the road traffic and guided buses operational. Oddly, when making the comparison, EWR Co have used a similar route to CBRR but, instead of using the CBRR trench construction methodology, they have taken an embankment solution and then proceeded to criticise it. The southern approach has a combined length of over 5km of embankment exceeding 8m in height. The trench approach has been presented on the CBRR website since 2018, so it is strange that EWR Co. do not even comment on it. Did they just miss it? Do they disagree with this widely used approach or are they just looking for reasons to justify a political decision made in favour of the southern approach and find this to be an inconvenient truth?

Impact on residents

This is one of the most important factors between a northern and southern approach, particularly in respect of noise. Night-time noise is clearly more problematic than day-time noise, so we believe that measures appropriate for freight services are more relevant than for passenger services. Although EWR Co have used a variety of assessments, including the length of railway in Cambridge wards, the most direct measure of this is the count of residential properties within 200m either side of the track. The length of track in Cambridge wards is not a very meaningful measurement because in some places the line passes through residential areas and in other places it does not. They have used Cambridge station as the basis for measurements: this is only appropriate for passenger services. We have also considered Coldham’s Common as a basis – see section above on ‘Assumptions and measuring points’. Our figures (which have been assessed by three separate people) are considerably less than those obtained by EWR. However, the absolute numbers are not critical for a comparison – it is the relative numbers between the northern and southern approach that matters. For passenger services the count is similar (slightly in favour of a southern approach) but the critical night-time freight measurement is massively in favour of a northern approach by a factor of over 8:1 (i.e. there are more than 8 times the number of residential properties within 200m of the track on a southern approach than a northern approach).

Roads and other crossings

The number of road and other crossings significantly impacts the overall construction cost of a railway. The greater the span of a bridge, the greater the cost so major road crossings affect the cost more than those for minor roads and farm-tracks. Assuming that 4-tracking will not be undertaken for whichever option is chosen, the overall result is in favour of a northern approach with slightly fewer A- and minor road crossings required. A more significant difference between the approaches is that because the northern approach would pass beneath existing roads, this would result in less temporary traffic disruption during construction and lower noise and visual impacts because of the trench technology.

Environmental factors

Measuring distances to environmental sites cannot reveal the whole picture of the impact of the railway on a site. This would partly depend on the wildlife or ecology that the site is trying to protect. For example, the railway following a southern approach can cause a lot of damage to the Wimpole and Eversden Woods SAC but this is not revealed by the measure EWR Co use to show the impact. Although we have compared the approaches using the same measures as EWR Co, they still need to be considered with some degree of caution.

SSSIs

There are 4 SSSIs within a 2km buffer of the southern approach but none on the northern approach. EWR Co have mistakenly measured the northern approach as having 1 within this distance. The one they counted was probably Madingley Woods which is about 2.3km from the northern route.

SACs

There are no Special Areas of Conservation (SACs) within any of the buffers used by EWR Co. This does not demonstrate the impact of the Southern Approach on the SAC at Wimpole and Eversden Wood in which a colony of Barbastelle bats roost. The bats forage for around 5-7km from the roosting site and would not be affected by the Northern route. See our previous post on this subject, the Wimpole/Eversdens SAC is one of only Barbastelle SACs in the UK and it is in great danger from EWR Co.’s cavalier assertions about mitigation techniques that have failed in the past and would fail here again

Scheduled monuments

The southern route impacts directly (within about 10m) on 3 scheduled monuments whereas there would be no direct impact with a northern approach. Even using a 2km buffer, the southern route fares worse.

Listed buildings

As for other environmental counts, EWR Co have measured two distances from listed buildings to assess the impact of each approach: 10m and 2km, and only using Cambridge station as the measuring point. We consider this to be misleading and have counted listed buildings within three different bands, 10m, 200m and 500m for both passenger trains and freight trains. While EWR Co’s assessment shows broadly similar impacts of both approaches (with a slight disadvantage for the northern route for grade 1 & 2* buildings), our more nuanced and thorough evaluation shows a clear and significant advantage for a northern route, even when considering passenger trains. As mentioned earlier, using Coldham’s Common as a basis for assessment is appropriate for freight trains which cause by far the bulk of noise and air pollution impact on all types of residential property. On this basis, our figures demonstrate that there are more than double the number of grade 1 and 2* properties within 500m of the track on a southern route than on a northern route. The difference is even more stark for grade 2 properties with over 4 times the number within 500m.

Priority habitats

EWR Co have counted the number of priority habitats within 10m and 2km of the alignments. This presentation fails to take account of the size of each habitat. To address this omission, we have considered the length of a 200m zone passing through each site[WH1] , as shown schematically below.


Figure 2 Measurement of priority habitats

Although imperfect, it is considered more accurate than EWR Co’s measure. EWR Co’s assessment results in broadly similar outcomes. However, our measure shows the southern route has about a 2.5 times greater impact than the northern route.

Wildlife Trust sites

There is an advantage of the northern route over a southern route (1 site compared to 2 sites within 2km of the routes) but, because the total numbers are low and the 2km distance is great, this is not a differentiating measure.

Local Nature reserves

Our figures are much lower than EWR Co’s figures for both alternatives so it is likely we have not been able to access all the data that EWR Co have used. But taking EWR Co’s numbers at face value, there is a nominal difference slightly in favour of a southern option (12 sites for a northern approach and 10 sites for a southern approach). Again, this is not a differentiating measure.

Residential properties

EWR Co include commercial as well as residential properties in their assessment, whereas we have considered only residential properties. As previously mentioned, they have also assumed that the West Anglia Main Line (Cambridge to Ely line) will be 4-tracked but without providing any supporting evidence. We dispute this assumption and consider that it could be left as a twin track line. Putting this argument to one side, we have looked in detail at EWR Co’s figures. We count 33 residential properties within 10m of the line that could be impacted by a northern approach with 4 tracks between Milton and Cambridge. This compares to 39 for a southern approach. EWR Co, on the other hand, count 40-85 residential and commercial properties close to the line for a northern route and just 5 for a southern route. We have measured to the boundary of a property. While we do not correlate these figures directly with the requirement for demolition, we consider that EWR Co have made some errors in their assessment. For example, there would be about 11 properties that would be directly impacted on just one site at Highfields Caldecote (the Linden development) on a southern approach.

Conclusions

The overwhelming message from our analysis is that on the vast majority of measures, the northern approach is superior to the southern approach, including embankments, residential impact, road crossings and environmental aspects. For the remaining factors, there is a broad similarity between approaches. The measure that EWR Co have ‘afforded particular weight in the back-check undertaken’, the impacts on residential properties, is broadly similar in our assessment even using the doubtful assumption that the northern route will need some 4-tracking.

Categories
news

Professor Emeritus David Feldman QC (Hon), FBA joins Cambridge Approaches legal team

The Cambridge Approaches legal team is very privileged to be joined by David Feldman.

David has taught, researched, written about and adjudicated in relation to law, especially constitutional and administrative law and human rights, including historical, comparative and philosophical aspects, for over 45 years. 

He has held many prestigious posts including Legal Adviser, Parliamentary Joint Select Committee on Human Rights, 2000-2004, Judge of the Constitutional Court of Bosnia and Herzegovina, 2002-2010 (a Vice-President 2006-2009) and Rouse Ball Professor of English Law, University of Cambridge, 2004-2018 (now Emeritus). He is an Academic Associate at 39 Essex Chambers, London and was elected Hon. Bencher at Lincoln’s Inn in 2003, elected FBA in 2006, appointed Hon. Q.C. in 2008 and awarded Hon. LL.D. from the University of Bristol in 2013. 

He is the author of a large number of books, articles, chapters and shorter works on many aspects of public, private and criminal law and procedure, including Civil Liberties and Human Rights in England and Wales 2nd edn (OUP, 2002), (as Ed.) English Public Law 2nd edn (OUP, 2009), and (as Ed.) Law in Politics, Politics in Law (Hart, 2013). 

Categories
Route Alignments

Rebuttal of EWR’s reasons for preferring a southern approach into Cambridge


Background

This post looks at East West Rail Company’s (EWR Co’s) arguments for rejecting a northern approach proposed by CamBedRailRoad (CBRR) and to provide the evidence to rebut their claims.

EWR Co presented their reasons in chapter 16 of the Preferred Route Option Report, issued in January 2020. (Preferred-Route-Option-Report)

They briefly set out the historic development of the approach into Cambridge from the south – it was based on Network Rail’s assessment in 2014 which was never discussed or consulted on with the public. EWR Co state that they have reviewed this decision before the last public consultation and that it ‘appeared to remain sound’.

Chapter 16 goes on to infer that the public supported this approach. Cambridge Approaches have already reviewed this claim in a previous post (CA post – fair consultation) and consider it to be flawed. In essence, EWR Co stated that a third of responses did not express a view, with the other two-thirds being broadly evenly split between agreeing and disagreeing with EWR Co’s decision to prioritise route options that approach Cambridge from the south and so implying that there no significant opposition to it. In fact, Cambridge Approaches more detailed and specific analysis from parish councils (which we took as proxy for public opinion) shows that almost three quarters of these parish councils either expressed a desire for a consultation on a northern approach (54%) or that there was insufficient information (17%) to make a choice.

Before we go on to review EWR Co’s arguments, we note that they have specifically removed the chord (track connection) proposed by CBRR on Coldham’s Common claiming that it:

  • would not serve Cambridge Station (it is not intended to serve Cambridge Station, at least for freight)
  • it would increase the capital cost of the project (yes, marginally, but needs to be assessed against the overall cost of the entire route options which we believe favours a northern approach)
  • it passes through a County Wildlife Site (yes, but again it needs to be balanced against all the other environmental sites of each approach option – a northern approach won convincingly when this was done (CA post – environmental-impact)).

In fact, this chord is essential to enable a connection from the north to connect with the eastern section of EWR without freight having to make a physical reversing move. Removing it implies that they did not understand how the CBRR route would function.

EWR Co have five main ‘selection criteria’ against which they claim all options are assessed. They have assessed the CBRR route against these criteria and use them as arguments for rejecting a northern approach. The criteria are:

  • Benefits for transport users
  • Supporting economic growth
  • Supporting delivery of new homes
  • Costs and overall affordability
  • Environmental impacts and opportunities.

16.19-22 – Benefits for transport users

From EWR Co’s analysis of including the CBRR-proposed stations at Northstowe and Cambridge North into their transport model, their conclusion is that the transport user benefits of a northern approach are £200m greater than a southern approach!

They go on to state that approaching Cambridge from the north would require a reversing move at
Cambridge station for any onward journeys to/from Ipswich, and to/from Norwich and that this would increase journey times. However, EWR Co state in their Technical Report (EWR-Technical-Report)

‘Onwards services to and from the east of Cambridge (for example to and from Norwich and Ipswich) are not currently included in the indicative train service specification for EWR services and are thus not part of EWR Co’s remit.’

We therefore wonder why this scenario is presented as an argument against a northern route. If additional services are included at a later stage, it is equally possible that onward services to Stansted could be included for which the CBRR route would be considerably more suitable than a southern approach. And again, they have removed the chord on Coldham’s Common that would allow freight trains to avoid such a reversing move.

16.23-25 – Supporting economic growth

EWR Co’s own conclusion on this ‘argument’ states:

‘The economic and employment opportunities provided around Cambridge North station and the proposed Cambridge South station are considered to be similar in nature and scale.’

There is, thus, no case to argue.

16.26-27 – Supporting delivery of new homes

EWR Co state in their argument that a northern approach would support the delivery of 10,000 homes that are planned at Northstowe. As this is one of the biggest housing developments in the UK since Milton Keynes, EWR Co seem to agree with us that this is a most convincing argument for a northern approach.

They go on to state that:

responses to the consultation did not identify any additional housing sites that could be supported if EWR were to approach Cambridge from the north’.

Below is schematic produced by CBRR showing existing, proposed and putative housing developments in the area. The black line is CBRR’s indicative route. The size of the circles represents the population of each site. To be fair, some of these sites have only come to light as a result of the publication of the call for sites by South Cambridgeshire District Council and that publication post-dates the option E decision. But this is the ‘new information’ that EWR Co have said they would need to if they were to reconsider the approach into Cambridge.

At a stroke, this contradicts EWR Co’s argument regarding supporting delivery of new homes. The schematic shows:

  • more new housing developments along the CBRR route than along the southern Option E one
  • more developments to the north of the Option E area near Cambourne and so provides justification for a north Cambourne station
  • a void of new housing development sites over the bulk of the Option E area.

Worryingly, EWR Co further state that:

‘Moreover, South Cambridgeshire District Council stated a preference for a route via Cambourne (Route E) that approaches Cambridge from the south.’

In fact, nowhere in SCDC’s response did they explicitly favour a southern approach over a northern approach. They supported Options B and E because they wanted EWR to serve Cambourne rather than Bassingbourn, not because it approached Cambridge from the south. They have highlighted the lack of information which would be required in order to make this decision.

‘Acknowledging the broad nature of this consultation, limited information available and significant uncertainties around growth implications, it is considered that, in principle, routes including Cambourne as a station (B and E) could be preferable to routes including Bassingbourn, for the following reasons:’ [SCDC’s underlining]

This is hardly the support that EWR Co imply.

16.28-31 – Costs and overall affordability

EWR Co consider that the upfront capital costs of the CBRR route is £600m more expensive than a southern approach. Given that the new track lengths may be broadly similar (depending on which southern alignment is chosen) and that a northern approach has about one third the number of road crossings, no river crossings and easier topography, we consider that a northerly approach may be cheaper to build than a southern approach, even allowing for a station at Northstowe.

EWR Co make allowance in their costings for crossing a new rowing lake north of Cambridge. However, the planning application for this rowing lake was withdrawn about 18 months before the EWR Co options report was published. It is therefore not an obstacle to the CBRR route.

However, the capital costs are only part of the financial picture. Revenues are the other part of the equation. EWR Co state:

‘The CBRR-based route would generate slightly higher revenues than Route B. However, these higher revenues are mostly offset by higher operating costs and whole life costs arising from the longer route and additional station at Northstowe.’ [CA underlining]

The word ‘mostly’ implies that, in fact, the greater revenues from the CBRR route more than compensate for any EWR Co-claimed additional construction costs.

Further information is provided in our post: CA post – capital costs.

16.32-34 – Environmental impacts and opportunities

The argument presented for the environment just lists issues with the northern approach. It makes no mention of the environmental impacts for a southern approach yet goes on to claim that:

‘A higher level of effort is therefore likely to be required to mitigate the effects of the presence of multiple environmental features compared to route options that approach Cambridge from the south.’

Not only is this illogical as they only present one side of the argument, but it flies in the face of the Wildlife Trust’s analysis. This clearly shows [CA post – environmental-impact] that there are approximately twice the number of environmental sites affected by a southern route than a northern one. The conclusion that a northern approach is more environmentally friendly is supported by Natural England, Cambridge Past, Present and Future and the Campaign for Rural England support northern approach. These organisations, unlike EWR Co who are based in Milton Keynes and Westminster, know the area well.

Not mentioned by EWR Co, but vitally important to residents, is the relative environmental noise and air quality impact of the two approaches. There are approximately 7 times (yes!) the number of properties within 200m of a representative southern route than the CBRR route.

Conclusions

In summary, we believe that EWR Co have a poor case for their approach into Cambridge. Far from justifying a southern approach, the evidence that we have provided strongly supports a northern approach. We have pointed all this out to EWR Co both in writing and at a recent meeting with the rail minister, Chris Heaton-Harris. Despite Mr Harris requesting that EWR respond promptly, we have yet (as of 16 March 21) to receive any reply.

Categories
news

Oct 8th Meeting Presentation

Below is a link to the PowerPoint presentation that was used at the meeting with Anthony Browne MP, EWR, SCDC, ‘Option E’ parish council representatives and Cambridge Approaches.

Although there was not unanimity, the majority of parish council representatives:

1) rejected the main body of the Option E area for EWR

2) supported a station to the north of Cambourne

Categories
news

Suggested topics in letters to Anthony Browne MP

Rather than providing a standard template letter for sending to our MP Anthony Browne, we suggest that you write individual letters to him that express your concern. MPs and their researchers have found that an original letter sent by a committed, passionate constituent is far more powerful than a pile of identical letters.

We have provided a list of topics below that you may wish to consider in writing your letter. We do not suggest that you include more than a few of them and only those that you feel strongly about. Your own words would be much more influential than using ours.

If you wish to obtain more information about any of the topics, please contact us and we will try to help.

PROBLEMS WITH OPTION E

Option E is the wrong solution – all feasible alternative alignments have significant problems.

  • There are no clear benefits to the Option E area, just the real long-term threat of creeping urbanisation along the line
  • Use of diesel locomotives rather than electrification from the outset – noisy and environmentally damaging option when the government has committed to reducing UK’s carbon footprint.  It is also massively more expensive to upgrade later than incorporating during the construction phase
  • Permanent loss of peaceful and beautiful countryside, especially if cuttings are used in some areas
  • Noise, especially from freight trains at night. This is likely to travel long distances from railway lines on embankments over flat and open countryside
  • Possible closure of roads and footpaths – this could have a devastating effect on the area by dividing communities. While EWR have provided verbal assurance that closure of public rights of way and roads would be a “last resort”, they have not confirmed this in writing despite specially being asked to do so
  • EWR’s poor business case for Option E, including new housing development and freight not being included – see blogs on Cambridge Approaches website. Option not demonstrably better than the alternatives – e.g. into Cambridge North rather than a planned Cambridge South station
  • Adopting a Cambourne North station rather than current Cambourne South. This view is strongly supported by Cambourne Parish Council as it is more convenient for the current and planned location of housing
  • No explanation of how much freight is planned on this line and how it gets to Felixstowe – there may well be further upgrades of existing lines or new lines near Cambridge in addition to those in the Option E area
  • EWR’s lack of transparency. All of Cambridge Approaches Freedom of Information requests have been rejected on the last day of the statutory consultation periods, partly for apparently pedantic reasons. The last FOI request was written with legal advice. Insufficient information has been provided to justify their business case.
  • Lack of coordination of the route with the Local Plan. This is fundamental to have an effective, cost-efficient and joined-up transportation system in the region that serves areas where there is greatest demand. This is demonstrably not the case for a route in the Option E area – the route to Cambridge North best serves existing and planned housing developments.
  • Low level publicity about the project. Many residents of the area have told Cambridge Approaches that they were totally unaware of the project before we distributed leaflets a few weeks ago, despite EWR holding a public consultation in early 2019.
  • Impact on farming – the railway line may disrupt farming in the area not only by losing increasingly valuable farmland but severing farm tracks and causing extra pollution by requiring farm vehicles to travel increased distances to access their land. There are several environmentally sensitive farms in the area, especially near Barton, that may be severely affected by the project.
  • Impact on ecology, including cutting of foraging routes and possibly disrupting the life of the rare Barbestelle bats in the Wimpole and Eversden Woods.
  • Impact on MRAO activities. These impacts may be able to be mitigated depending on the proximity of the railway to active telescopes. You may think that disruption to MRAO’s activities is better than potentially running the line close to villages. Alternatively, you may believe that MRAO’s presence in the area has limited much development that would have otherwise occurred. As a compromise, it may be possible that MRAO could move their telescopes, as they did several years ago, to a less sensitive part of their site.
  • Greater use of tunnelling in difficult areas that would otherwise cause severe environmental damage

REQUESTED ACTIONS BY ANTHONY BROWNE

Call for Anthony Browne to lobby government and EWR:

  • to reject Option E
  • to investigate options that follow existing or planned transport corridors (e.g. A428 & M11) in accordance with the National Infrastructure Commission report (Partnering for Prosperity: A new deal for the Cambridge-Milton Keynes-Oxford Arc). These should include a route to Cambridge North rather than Cambridge South
  • to consider the environment to a greater extent than EWR are doing already, especially in their choice of whether to adopt an electrified line at the outset
  • to provide the public with clear and unambiguous information to back up their decisions, especially in terms of value-for-money of various alignment options and in fulfilling their environmental pledges.
Categories
news

Radio telescopes and discussions with MRAO

Richard Saunders from Cambridge University Mullard Radio Astronomy Observatory (MRAO) spoke to David Revell from Cambridge Approaches on August 31 about discussions taking place between EWR and the MRAO. Richard said that the discussions were at a very early stage and were intended to help each side understand the other’s technical constraints and issues: they were definitely not at the ‘negotiating’ stage.

Richard mentioned that issues included the electro-magnetic interference from the side-to-side movement of the trains.

Line of sight issues (for example, depending on where a telescope may be pointing) are difficult to mitigate against. EWR had said that locally lowering the track would not be feasible due to the high water table and Richard said that raising the telescopes was not possible either. He said that the geographic bowl in which the telescopes sit is pretty unique in the UK and that electrical simulation tests would have to be undertaken to fully understand the impacts.

The extreme sensitivity of the MRAO equipment to vibration dictates that any mitigation against vibration of the telescopes from the trains would have to be exceptionally effective.

EWR were understood not to be totally averse to moving outside the Option E area if essential, or of providing tunnels per se but drainage of the tunnels would need an alternative to a pumped solution.

Richard was conscious of the need to minimise the environmental impact on the area by the railway, including noise, visual and ecological impacts.

Categories
Route Alignments

EWR’s Possible Rail Routes

What happens if we do nothing?

**** For people new to this website: Cambridge Approaches favours a northern approach to Cambridge. Routes in this post are showing what might happen if we don’t do anything. They are not routes that are endorsed by Cambridge Approaches. ***

We have analysed potential routes that EWR could take within their Option E’ corridor and those are explored above. None of these options are favoured by Cambridge Approaches but does show what the impact on communities within the route alignment.

At the time of writing, these options are under review by local parish councils forming the Cambridge Approaches Oversight Group at a series of meetings including the Cambridge Approaches Working Group.

EWR’s options, which they intend to issue in Q1 in 2021, may differ from those shown.

We invite comments below.

You can download the map here.